Case ID:182123
Parties: None
Date Delivered: None
Case Type: None
Court: None
Judges: None
Citation: None
Home Bridge Limited v Tatu City Limited [2021] eKLR
Case Metadata
Case Number:
Environment and Land Case E077 of 2021
Parties:
Home Bridge Limited v Tatu City Limited
Date Delivered:
24 Sep 2021
Case Class:
Civil
Court:
Environment and Land Court at Thika
Case Action:
Ruling
Judge(s):
Lucy Nyambura Gacheru
Citation:
Home Bridge Limited v Tatu City Limited [2021] eKLR
Court Division:
Environment and Land
County:
Kiambu
Disclaimer:
The information contained in the above segment is not part of the judicial opinion delivered by the Court. The metadata has been prepared by Kenya Law as a guide in understanding the subject of the judicial opinion. Kenya Law makes no warranties as to the comprehensiveness or accuracy of the information
REPUBLIC OF KENYA
IN THE ENVIRONMENT AND LAND COURT
AT THIKA
ELC CASE NO. E077 OF 2021
HOME BRIDGE LIMITED………………………… PLAINTIFF/ APPLICANT
VERSUS
TATU CITY LIMITED……….………………….DEFENDANT/ RESPONDENT
RULING
The matter for determination is the
Notice of Motion Application
dated
21
st
July 2021,
brought by the Plaintiff/Applicant seeking for orders that;
1. That this Honourable Court do grant a temporary injunction restraining the Defendant/Respondent either by itself or through its Directors, Servants or Agents from interfering with the construction, sale occupation and quiet possession of Block 18 –Lifestyle Heights Estate erected on a portion of Precinct 4B-2 forming part of Land Reference No. 28867/1 pending the hearing and determination of this suit
2. That the costs of this Application be provided for
3. That this Honourable Court do grant further or any other orders that it may deem fit to grant.
The Application is premised on the grounds that the Plaintiff/ Applicant entered into a lease agreement dated
20
th
July 2016,
and
22
nd
August 2016,
respectively with the Defendant/Respondent as Lessee and Lessor respectively to lease unit
No. L4 -01 and L4-02,
measuring
30 acres
or thereabouts being Precinct
4B-2,
forming part of
L.R 28867/1.
That the Lease provides that the Defendant/ Respondent has an obligation to incorporate
Precinct Owners Association
and various
Properties Owner Association,
for every Precinct to operate and manage matters specific to the respective precincts. Further, that the Defendant/ Respondent is governed by a Master Declaration of Covenants conditions and restrictions dated
30
th
July 2014,
between the Defendant/Respondent and
Tatu City Property Owners Association
. That the Master Declaration establishes a
Development Control Committee(DCC),
appointed by the Defendant/ Respondent with an obligation to issue approvals of any final construction drawings and specifications before commencement of any construction, and/or improvement of any parcel.
That the Plaintiff/ Applicant obtained the necessary approvals from the
DCC
for
L.R 4B-02,
vide a letter dated
15
th
November 2016, and
approval of parcel
No. L4-01
vide letter dated
18
th
February 20819,
erected on a portion of
Precinct 4B-2,
forming part of
L.R 28867/1.
That the Plaintiff/ Applicant further obtained approvals from the
County Government of Kiambu,
in accordance with the Lease and the Master Declaration. That subject to the said approvals, the Plaintiff/ Applicant commenced construction of
Block 18-Lifestyle Heights Estate,
which is at an advanced stage of development. Further, that the Plaintiff/ Applicant advertised and commenced the sale of the units of
Block 18,
which sale is by way of
off plan
and therefore any interference with the construction , sale, occupation and quiet possession of
Block 18,
will occasion financial loss to third parties. That despite obtaining approvals, the
DCC
issued a
Stop Order
vide a letter dated
9
th
March 2021,
halting the construction of
Block 18
. That the Plaintiff/ Applicant has invested colossal sums of money into the purchase, construction and development of the suit property, making it the largest project in
Tatu City
. That the Defendant’s / Respondent’s allegations that the Plaintiff/ Applicant has failed to get
DCC
approvals are misguided and an afterthought. Further that the said
Stop Order,
is malicious and intended to occasion loss to the Plaintiff/ Applicant and it is therefore not plausible under what circumstances the approved drawings were purportedly cancelled.
That the Defendant/ Respondent has acted in breach of the Plaintiff/ Applicant’s legitimate expectation as the
Stop Order
was issued after the approval had been granted by the Defendant/ Respondent. That the Defendant/ Respondent’s actions are in
bad faith
and
intended
to
hurt
the development project. The decision is unreasonable and meant to deprive the Plaintiff/ Applicant of its lawful right of the use of the property.
That the Plaintiff/ Applicant commenced construction following the advice, assurance and subsequent approvals by the Defendant/ Respondent and therefore the Defendant/Respondent cannot be allowed to allege that the construction was without approval.
In his Supporting Affidavit,
Peter Murage Karoki,
the Director of the Plaintiff/ Applicant averred that the Plaintiff/ Applicant by way of a letter dated
5
th
July 2021,
issued a demand to the Defendant/ Respondent to lift the
Stop Order;
However, the Defendant/ Respondent has refused to make good the Applicant’s claim. That it is in the interest of justice to ensure that the underlying claim is not rendered nugatory and otherwise superfluous by the mischievous actions of the Defendant/ Respondent, and thus it is only fair that the Orders sought are granted.
The Application is opposed and the Defendant/ Respondent filed a Replying Affidavit sworn by Alex
Kahu Kamuhia,
on
9
th
August 2021
who is the
DCC
Chairman, and who averred that
Clause 1.4,
of the Master Declaration provides for among other purposes protection of the investment of the owner of each parcel against such improper development and undesirable use of surrounding parcels, as will depreciate the value of the remaining parcels. Further, that
Clause 8.3,
of the Master Declarations, provide that the
DCC
has a right to disapprove any final construction drawings/ Specifications for failure to comply with the Master Declaration. That
Clause 6.7.4,
of the Lease required that the Plaintiff/ Applicant to ensure that erection or alteration or extension made on any building is in accordance with the building plans submitted and approved in writing first by the
DCC
and thereafter the
Kiambu County Government
.
That on
15
th
November 2016,
the
DCC
approved the Plaintiff’s/ Applicant’s building plans reference
number 201611-15-4B-02-LH’
subject to approval by the
Kiambu County Government
. That the Defendant’s/Respondent’s property is adjacent to
Kijani Ridge
and
clause 6.7.2,
provides that the Plaintiff/Applicant shall ensure that the building constructed would not in any way devalue the neighboring properties and specifically does not block or overlook the properties in
Kijani Ridge.
That during the review of the approval, the Plaintiff/ Applicant explained that in order to comply with
Clause 6.7.2,
the building blocks adjacent to
Kijani Ridge
would have a
ground floor,
plus additional levels within the profile rising towards the South. Further, that under
Clause 8(1),
of the approval, the Plaintiff/ Applicant was required to ensure that any ,modification of the building plans were approved by the
DCC
in writing before such modifications were effected. That the Plaintiff/ Applicant requested and was granted an approval of the amended plans by the Defendant/ Respondent on
18
th
February 2019 .
That the Plaintiff/ Applicant in breach of its obligations under the
Master Declarations
and the leases proceeded to construct ground floor plus four floors contrary to the approved plans. That via an email date
4
th
March 2021,
the
DCC
informed the Plaintiff/ Applicant that it had noted the ongoing constructions and requested for the designs for the new block for review, Further that by a letter dated
8
th
March 2021,
the
DCC’s
architect gave its observations on the project and confirmed that all the Plaintiff/ Applicant building blocks next to
Kijani Ridge,
ought to be a minimum of four floors and on
9
th
March 2021
, the
DCC
issued a
Stop
Order
on the construction, until the requisite
DCC
and statutory approvals were procured and requested the Plaintiff/Applicant to submit the reviewed designs for approvals.
Further that by a letter dated
11
th
March 2021
, the Plaintiff/ Applicant informed the Defendant/ Respondent that it had complied with all approvals and requested for a meeting to amicably resolved the dispute . That on
12
th
March 2021
, the Defendant/ Respondent reiterated that no drawings to increase floors were submitted to the
DCC,
and by a letter dated
16
th
March 2021
, the Plaintiff’s/ Applicant’s Contractor confirmed that it will comply with the said
Stop Order,
and requested for a meeting for review session of the design amendment . Further, that on
24
th
June 2021
, the Defendant/ Respondent informed the Plaintiff/ Applicant that the design and letters of the building were significantly different from the architectural design and letters submitted to the
DCC
and the Defendant/ Respondent instructed its Advocates to issue a
demand notice
for violation of the Building Plans. That the Defendant/ Respondent cannot be held liable for damages, and/or losses incurred by the Plaintiff/ Applicant from advertising and offering for sale. That the Plaintiff/ Applicant is not deserving of any injunctive orders as the same would have the effect of allowing a construction to continue contrary to the building plans as approved.
The Plaintiff/ Applicant filed a Supplementary Affidavit sworn by
Peter Murage Karoki
on
6
th
August 2021,
who averred that sometimes in the year
2018
, the Plaintiff’s/ Applicant’s submitted revised building plans in respect of the suit property to
DCC
for approvals and that the same were an amendment to the
2016,
approved plans and by the amendment, the Plaintiff/Applicant proposed to build five floors, comprising of the ground floor plus four floors , instead of the previously approved ground floor plus three floors. That the
DCC
gave its approvals on
13
th
February 2019,
and the said amended building plans were submitted to
Kiambu County Government
and through its letter dated
19
th
October 2019,
the County Government approved the plans and the Applicant’s proceeded with the construction.
The Applicant filed a Further Affidavit sworn on
16
th
August 2021,
by
Bob Oyugi, the
/Plaintiff’s/Applicant’s
Project Architect,
who averred that the Applicant fully adhered to the requirement stipulated
under Clause 6.7.4,
of the Master Declaration by submitting the plans for approval. That the Defendant/ Respondent granted full and unconditional approval of the building plans as submitted by the Plaintiff/Applicant and no issue of obstruction was raised and in the impugned
Stop Order
, no issue of obstruction was raised. That if obstruction was an issue, the same ought to have been raised during inspection and review of the building plans by the
DCC,
when the amendments were submitted.
That the annexures produced by the Defendant/ Respondent in its Replying Affidavit, related to the initial drawings submitted by the Applicant for discussions and review in respect of which the approval was issued in
November 2019
. That the said drawings are not approval drawings . That the amendment submitted by the Applicant in 2019
,
sought the
DCC
approvals to construct an additional floor on
blocks 11,12,18,19 & 20,
and the Plaintiff/Applicant was allowed an additional level . That the building plans produced by the Defendant/ Respondent are not the
final building plans,
and were just
working
documents,
subject to amendments and revisions. That the letters issued by the Defendant/ Respondent and the
Stop Order,
were mere afterthought, and the Construction of the new level on
Block 18
was done with the
DCC
approvals. That the amendments did not in any way change the architectural design.
The Defendant/ Respondent also filed a Further Replying Affidavit sworn by
Peter Njoroge Mwaura,
on
25
th
August 2021
, and averred that the invoice from the
Kiambu County Government
was paid before the
DCC
issued its approval on
18
th
February 2019 .
That by submitting the Architectural Plans directly to the
Kiambu County Government
, the Plaintiff/ Applicant violated and breached the requirements of the approval letter since the
DCC
was required to submit the architectural plans on their behalf. That there are 3 sets of building plans in question and the
DCC
was only aware of two sets of building plans that were submitted to the
DCC
for approval. That the
Stop Order
was issued after the Plaintiff/ Applicant had commenced construction, and it was clear that the construction in
Block 18,
was not in accordance with the building plans approved by the
DCC
. That the approval letters issued in
2016,
and
2019,
were based on submitted sets of building plans that showed the elevation of the various blocks and that the
DCC
is allowed to review the building plans from time to time. That if there were any other amendments made, the same ought to have been submitted to the
DCC
for approval before the Plaintiff/ Applicant could commence construction . That the
DCC
did not approve construction based on the drawings produced as annextures
PMK 10 and PMK 11
on the Plaintiffs/ Applicants Supplementary Affidavit.
That the
DCC
approved the modifications of
Block 18
to include one additional floor, from ground floor plus by converting the terrace to habitable floor , Further that the
DCC
would not approve working drafts as alleged, and the
DCC
is mandated to issue
Stop Orders
for offending Developments and the Notice of Violation and
Stop Order
issued on
9
th
March 2021,
require the Plaintiff/ Applicant to stop all construction and submit the revised designs of
Block 18
for review and it is incorrect for the Plaintiff to state that the issue of architectural designs is a new issue. That the
Stop Orders
were issued to ensure that the low density precinct of
Kijani Ridge
was not negatively impacted by the Construction of
Block 18,
contrary to the approved building plans.
The Plaintiff/Applicant filed a 2
nd
Further Affidavit sworn on 3
rd
September 2021,
by
Bob Oyugi,
who averred that the Applicant made payment in respect of the amended plans before
18
th
February 2019,
when the
DCC
issued its approval . That in the absence of a precondition for the
DCC
to present the building Plans for approval on behalf of the Applicant, the Applicant was entitled to lodge the approved plans, with the County approval and having obtained the
DCC
approval, there was nothing unusual with the Applicant lodging the amended plans with the County Government for approval. That the building plans, submitted to the
DCC
for approval in
2018
and which were approved on
18
th
February 2019
were the exact same plans that were submitted to the
County Government of Kiambu;
That the terrace was already an existing floor by itself and hence the addition on additional floor could only have been a floor above the terrace .
That the impugned
Stop Order
was issued twelve months after the construction works had began on the suit property and the issue of height being raised when the building is 90% done and substantially sold to third parties is in bad faith and the Applicant has not violated the provisions of the Lease . That the Applicant has demonstrated that it had all the requisite approvals before commencing the construction and also come to Court with clean hands.
The Application was canvased with by way of written submissions which the Court has carefully read and considered. The Court has also read and considered the pleadings in general, the instant application, the affidavits filed together with the annextures thereto and the relevant provisions of law and finds that the issue for determination is
whether the Plaintiff/ Applicant is entitled to the injunctive orders sought
.
The Plaintiff/ Applicant has sought for temporary injunctive orders and he is entitled to either grant or denial of the same at this interlocutory stage. At this stage, the Court is not called upon to determine disputed facts and or facts that ought to be determined at the main hearing on the basis of contradictory Affidavits evidence . . All that the Court is required to do is to determine whether the Applicant is deserving of the Orders sought. See the case of
Airland Tours and Travel Ltd…Vs…National Industrial Credit Bank, Milimani HCCC No.1234 of 2003
, where the Court held that: -
“
In an Interlocutory application, the Court is not required to make any conclusive or definitive findings of facts or law, most certainly not on the basis of contradictory affidavit evidence or disputed proposition of law”.
In determining whether to grant or not to grant the orders sought, the Court will be guided by the principles set out in the case of
Giella …Vs… Cassman Brown Co Ltd ( 1973)EA 358
, and which have also been reiterated in other determinations. See the case of
Kibutiri…Vs…Kenya Shell, Nairobi High Court, Civil Case No.3398 of 1980 (1981) KLR
, where the Court held that: -
“The conditions for granting a temporary injunction in East Africa are well known and these are:
First
, the Applicant must show a prima facie case with a probability of success
. Secondly
, an interlocutory injunction will not normally be granted unless the applicant might otherwise suffer irreparable injury which might not adequately be compensated by an award of damages.
Thirdl
y, if the Court is in doubt, it will decide an application on the balance of convenience. See also
E.A Industries ..Vs...Trufoods (1972) EA 420.”
The Applicant is first required to establish that it has a
prima-facie
case with probability of success. A p
rima-facie
case was described in the case of
Mrao Ltd…Vs…First American Bank of Kenya Ltd & Others (2003)KLR
, to mean:-
“A case in which on the material presented to the Court, a tribunal properly directing itself will conclude that there exists a right which has apparently been infringed by the opposite party as to call for an explanation or rebuttal from the latter”.
Further a prima facie case was defined by
Mustill J in The Ledersachsen [1983] 2 Lloyd's Rep 600 at page 605
to be a good and arguable case which connotes one which is more than barely capable of serious argument, but not necessarily one which the Judge considers would have a better than 50% chance of success”.
It is not in doubt that the Defendant/ Respondent is the owner of L.R
28867/1.
Further, it is not in doubt that the Plaintiff/ Applicant purchased some units, being a portion of a precinct forming part of the said property. It is thus not in doubt that the suit property forming the dispute in the instant suit is owned by the Plaintiff/ Applicant, being a Lessee of the said property. This would automatically mean that the Plaintiff/Applicant has an interest in the said suit property.
In the case of
Mrao(supra),
a prima facie case is defined to mean that …
that there exists a right which has apparently been infringed.
The Court noted and found that the Plaintiff/ Applicant herein has a right over the suit properly, given that it is a Lessee of the said property. The Plaintiff/ Applicant has contended that according to the sale agreement with the Defendant/ Respondent, it was allowed to construct on the suit property subject to the approvals of the
DCC.
This approval according to the Plaintiff/Applicant was sought and granted, but the Defendant/ Respondent has now sought to serve it with a
Stop Order
. From the events that have unfolded, it is evident that a tribunal properly
directing itself would find that a right in this case for the Plaintiff to construct on the suit properly has allegedly been breached. Therefore, the Court finds and holds that the Plaintiff/Applicant has established
a prima facie case,
with a probability of success.
The principles as set out in the locus Classicus of
Giella …Vs… Cassman Brown
are sequential in nature and therefore upon establishing a prima facie case, the Plaintiff/ Applicant is further required to show that it will suffer irreparable harm that cannot be compensated by way of damages In the case of
Gitonga Wanjau…Vs…Gathuthi Tea Factory Co. Ltd & 2 Others, Nyeri HCC No.28 of 2015
, an irreparable injury was defines as
simply injury or harm that cannot be compensated by damages and would be continuous.
Further in the Case
of
Niaz Mohammed Janmohamme …Vs… Commissioner for Lands & 4 Others (1996) eKLR
, the Court held that: -
“It is no answer to the prayer sought, that the Applicant may be compensated in damages. No amount of money can compensate the infringement of such right or atone for transgression against the law, if this turns out to have been the case. These considerations alone would entitle the Applicant to the grant of the orders sought”.
Again in the case of
Muiruri vs Bank of Baroda (Kenya Ltd (2001) KLR 183 at Page 188,
the Court held that;
“
besides disputes over land in Kenya evoke a lot of emotions and except in very clear cases, it cannot be said that damages will adequately compensate a party for its loss”
The Plaintiff/Applicant has allegedly sold the units herein
off plan
to 3
rd
parties and the loss that would be incurred if the construction is stopped at instance stage would not adequately be compensated by an award of damages as besides the Plaintiff/Applicant, said 3
rd
parties would be affected both psychologically, emotionally and financially.
It is clear that the Plaintiff/Applicant had sought for and was granted approval by first the
DCC
and secondly the
Count Government
of Kiambu
to commence Construction on the suit property. By a subsequent Amendment by the Plaintiff/Applicant which sought to include on the building plans another floor, the said amendment was approved by the
DCC.
However, therein lies the point of dispute by the parties. While the Plaintiff/ Applicant has averred that it was allowed to
add more floors above the terrace, it is the Defendant’s/ Respondent’s contention that the terrace was supposed to be turned into another floor and that the building plans submitted by the Plaintiff/ Applicant as annexture
PKKK 11
in Plaintiff’s Supplementary Affidavit is not the building plans that the
DCC
approved.
The Defendant/ Respondent in its submissions has invited the Court to determine whether the Plaintiff/ Applicant is in breach of its contractual duties and whether the Defendant/ Respondent had a right to issue stoppage orders. A perusal of the Amended Plaint filed by the Plaintiff/ Applicant reveals that the issue of the
Stop Order
is at the core of the suit. Whether or not the building plans were the one approved and or the
stoppage order
was legal, are issues that go to the merit of the suit. As noted above, this Court is unable to determine the said issues at this interlocutory stage as these issues can only be determined when the Court is in position to take evidence from the parties and then weigh the said evidence adduced and thereafter come up with a conclusive finding.
What is not in dispute is that approvals were granted, and for the Court to determine which approvals were granted, the same would be done during the main hearing. However, it is clear that the Plaintiff/ Applicant was building units that are
off plan
. The Contention by the Plaintiff/ Applicant that the said units have already been sold to
third parties
has not been rebutted by the Defendant/Respondent. Further it has not been rebutted that the said construction is 90% done. This Court takes
Judicial Notice
of the costs of construction and the kind of labour involved. Further, the Court takes cognizance of the fact that whenever a construction is halted or stalled, there are financial repercussions together with the wear and tear of buildings that have been left incomplete. There is also an issue of Contracts entered into between the Plaintiff/ Applicant and the third parties. It is the Court’s considered view, that in view of the fact that there ware approvals that had been granted to the Plaintiff/ Applicant and the only issue is to what extent, if the construction is stopped and after the trial, the Court finds in favour of the Plaintiff/ Applicant, then the Plaintiff/Applicant it would have suffered irreparable injury, which cannot adequately be compensated by an award of damages.
The Court is also called upon to decide where balance of convenience lies. In the case of Pius
Kipchirchir Kogo …Vs… Frank Kimeli Tenai (2018) EKLR which
defined the concept of balance of convenience as:
‘The meaning of balance of convenience in favor of the plaintiff' is that if an injunction is not granted and the Suit is
ultimately decided in favour of the plaintiffs,
the inconvenience caused to the plaintiff would be greater than that which would be caused to the Defendants if an injunction is granted but the suit is ultimately dismissed. Although it is called balance of convenience it is really the balance of inconvenience and it is for the plaintiff’s' to show that the inconvenience caused to them be greater than that which ma)' be caused to the Defendant’s inconvenience be equal, it is the plaintiff who suffer.
In other words, the Plaintiff have to show that the comparative mischief from the inconvenience which is likely to arise from withholding the injunction will be greater which is likely to arise from granting”
This Court is not in doubt. However, keeping in mind the above analysis, it is the Court’s considered view that the prejudice that would befall the Plaintiff/Applicant if the injunction Orders are
not granted
far outweigh that which would befall the Defendant/ Respondent as all that would be required in order for the Defendant/ Respondent to fulfil their rights if the Court was to find in its favour is that the Court would Order the Plaintiff/ Respondent to demolish the said extra floor. The Defendant/Respondent would not suffer any prejudice if the injunctive orders are granted. The Court finds and holds that the balance of convenience lies in favour of the Plaintiff/ Applicant herein.
The Upshot of the foregoing is that the Court finds and holds that the Plaintiff/ Applicant has met the
threshold
for grant of the injunctive orders sought and the Applicant is consequently entitled to the Orders of injunction as sought in the instant application. Consequently,
the Court finds and holds that the
Notice of Motion application
dated
21
st
July 2021,
by the Plaintiff/ Applicant
is merited
and the same is allowed entirely with costs to the Applicant herein.
It is so ordered
Dated, signed
and
Delivered
at
Thika
this
24
th
day
of
September, 2021
L. GACHERU
JUDGE
Court Assistant – Lucy