Paul Opuko Ongurambe & 40 others v National Land Commission & another [2020] eKLR
Case Metadata
Case Number:
Environment and Land Case 66 of 2020
Parties:
Paul Opuko Ongurambe & 40 others v National Land Commission & another
Date Delivered:
12 Nov 2020
Case Class:
Civil
Court:
Environment and Land Court at Kitale
Case Action:
Ruling
Judge(s):
Francis Mwangi Njoroge
Citation:
Paul Opuko Ongurambe & 40 others v National Land Commission & another [2020] eKLR
Court Division:
Environment and Land
County:
Trans Nzoia
Disclaimer:
The information contained in the above segment is not part of the judicial opinion delivered by the Court. The metadata has been prepared by Kenya Law as a guide in understanding the subject of the judicial opinion. Kenya Law makes no warranties as to the comprehensiveness or accuracy of the information
REPUBLIC OF KENYA
IN THE ENVIRONMENT & LAND COURT
AT KITALE
ELC CASE NO. 66 OF 2020
PAUL OPUKO ONGURAMBE AND 40 OTHERS....................................................APPLICANTS
VERSUS
NATIONAL LAND COMMISSION AND ANOTHER........................................RESPONDENTS
RULING
1. The applicants filed an application dated
29/10/2020
seeking an order that the
status quo
concerning the suit land be maintained by prohibiting the respondents from continuing with compulsory acquisition of land measuring 108.6 acres for construction and upgrading of the Kitale –Endebess –Suam road (C45) and/or from in any other way interfering with the plaintiff’s interests in their respective lands and/or businesses.
2. The respondents never filed any reply to the application despite service upon them which was supported by the affidavit of service of Archibald Wekesa Nyukuri filed in court on
5
th
November 2020
.
3. The application is therefore unopposed. On
6/11/2020
when the application came up before this court for hearing Mr Teti for the applicants prayed that it be granted as prayed and this court granted a temporary order in terms of
prayer no (2)
thereof and reserved the matter for a ruling on
12/11/2020
.
4. As the application is unopposed, I hereby grant it but only to the extent that during the construction of all that infrastructure referred to as the Kitale–Endebess – Suam road (C45), the respondents shall not in any manner interfere with the plaintiff’s interests in their respective lands and /or businesses located thereon pending the hearing and determination of the suit.
5. The parties shall comply with the rules and file their bundles of documents and lists and this matter shall be mentioned on the
2
nd
December 2020
for confirmation of such compliance and for fixing a hearing date.
Dated, signed
and
delivered
at
Kitale
via electronic mail
on this
12
th
day of
November,
2020.
MWANGI NJOROGE
JUDGE, ELC, KITALE